The State Government and DPTI have advised that Jetty Road, Glenelg, will be closed to traffic during the period 15th May to the 9th June. Partridge Street General Practice will be OPEN and it will be business as usual for us and our valued patients. Aspire Physiotherapy and Pilates, Sense Podiatry, Helen at Family Nutrition and Diabetes Services, and Dr Amber Keast will also be OPEN as usual.

The main points are:

 

 

Tram Tracks Replacement Project

About the project

During May and June 2017, the Department of Planning, Transport and Infrastructure (DPTI) will be replacing tram tracks along Jetty Road, Glenelg.

These works are necessary as the existing tram tracks and associated infrastructure have reached the end of their useful life. New rail and associated infrastructure will be installed to ensure the continued safe and reliable Glenelg tram services are provided for the 9.23 million passengers using this service each year. Cyclist safety will also be improved with an upgrade to Tram Stop 16 on Jetty Road, as part of the project.

Project completion is expected at the end of June 2017.

Jetty Road closure

To minimise disruption to tram passengers, businesses, residents and visitors to the Jetty Road precinct, the works will be undertaken during the planned closure of Jetty Road from 15 May – 9 June 2017 inclusive.

DPTI appreciates your patience and cooperation whilst these important works are undertaken.

 

 

road closures partridge glenelg jetty road tram

Date change! May 15-June 9!! Reach Partridge Street General Practice via High Street or Partridge Street South of Jetty Road

During the closure of Jetty Road

 

 

Tram services to Glenelg will terminate at Stop 15 Brighton Road, with normal services to resume from mid June 2017.

Bus services that use or cross Jetty Road will be re-routed to avoid the construction site and will follow the bus routes used during major events. For information about the temporary routes, please visit www.adelaidemetro.com.au or alternatively please visit www.adelaidemetro.com.au/user/register to sign up to My Metro to receive updates when there are changes to travel conditions, straight to your inbox or mobile phone

Traffic detours will be in place throughout the closure with signage and traffic controllers advising motorists of the changed traffic conditions. Road users are requested to observe traffic signs and restrictions.

Pedestrian access to businesses along Jetty Road will be maintained at all times during the closure period, with pedestrians able to cross Jetty Road at Brighton Road, Moseley Street and Moseley Square. An additional pedestrian crossing will be provided on the western side of the intersection of Jetty Road with Gordon and Partridge Streets.

Car parking along Jetty Road will not be available during the construction period. Signage will be in place to direct motorists to alternative public parking sites. Disabled parking will be relocated 60 metres north of current locations and clearly identified with signage.

Loading zones located in side streets and to the rear of businesses will remain in place during construction. However, loading zones on Jetty Road will be temporarily removed during construction and relocated to side streets in close proximity to Jetty Road.

Haulage routes

During the construction period, large trucks will access the site to deliver materials including steel rails and remove construction waste such as concrete. Heavy machinery will also need to be transported to and from the work site.

Heavy vehicles will be restricted to main roads wherever possible including Anzac Highway, Colley Terrace, Jetty Road and Brighton Road. Occasionally, heavy vehicles will need to use local streets to access Jetty Road, however this will be mitigated where possible.

Construction machinery associated with the works will be stored at the southern end of Byron Street, Waterloo Street, Nile Street and Sussex Street. Pedestrian access to Jetty Road will be maintained at these locations.

A site compound will also be established on the Jetty Road end of Nile Street.

 

For more information

 

If you have any further enquiries please telephone 1300 030 919 or email DPTI.CommunityRelations@sa.gov.au

 

img_0766-7

 

 

 

Partridge Street General Practice will be OPEN according to our usual hours, for this whole period.

830am-5pm Monday to Friday (excepting public holidays)

830am-1230pm Saturday